DEVELOPMENT WORK AT HBR LAYOUT 5TH BLOCK


H.B.R LAYOUT 5TH BLOCK RESIDENTS ASSOCIATION


D.No.1489, 17th C main, 5th block, HBR layout, 1st stage, Bangalore-560043

____________________________________________________________________

To                                                                                                                       5th Jan ‘09
Shri.S.C.Jayachandra, B.E, K.E.S
Chief Engineer (East), BBMP,
P.U Building, M.G. Road ,
Bangalore-560001 (via email: report.ceeast@rediffmail.com)

Dear Sir,

Sub: Development work in HBR layout 5th block.

Further to our letter(attached) dt:29th Dec 09, we would like to inform you that de-silting work in SWD and removal of debris in 30th C cross (KEB road) are stand still as it was and no work has been done after 24th Dec. The silt removed from SWD is lying on both sides of SWD along with the debris on KEB road, which needs to be removed. Please have a look at these photos taken today so that you will under stand the condition of SWD and the road.

On 30th Dec one JCP used for debris removal, came at around 11 am but without truck, did some leveling work in 30 C cross and left at 1.30 pm. We don’t understand why the JCP should come without truck and spend some time and go back without doing any work. We know the JCP’s per hour cost is high and we have to use it to the maximum extent. We have noticed that many times the JCP comes and goes without any justification.


Silt removed from SWD along with debris lying in 30th C cross (KEB road)
We further wish to inform you one more thing is that the driver of the JCP used for debris removal is always seeking our directions “what is to be done in this layout.” Actually some supervisor should accompany the vehicle and get the things done.

                                     De silting work not done properly,yet to be completed
Please note that the uncompleted de-silting work is done from outer ring road to 19th main road bridge only, say approx. to a length of 400 meters, but not 700 meters as you mentioned; and de-silting work beyond the bridge also to be taken up. We don’t get any proper response from Mr.Vijayakumar and his assistant Mr. Kumar; we get lame excuses from them for why the work is not taken up when enquired.

We have already mentioned in our earlier letters that engineers of BBMP in charge of our layout are not visiting/inspecting while the developmental work is under progress.

We are also sending some of the videos showing the silt and debris lying along the cleaned stretch of SWD.
We request you to kindly monitor the on going work and see that all the pending works goes on smoothly without any stoppage.
Thanking you,
With regards
A.Rajagopal
Treasurer
Copy to:
Mr. Bharath Lal Meena, I.A.S
Commissioner, BBMP,
Bangalore . ( with a request to look into the matter).

Attachment: Videos MOV00439mpg; MOV00443mpg; MOV00444 mpg